Before installation
Confirm that building work is complete enough for kitchen fitting: floors and walls should be ready, services positioned according to the approved plans and the site accessible. Check deliveries and storage space before installers arrive.
A final dimension check is essential because drawings and existing rooms do not always match.
Cabinet fitting comes first
For made-to-measure stone or porcelain worktops, the cabinets are normally installed, levelled and fixed before the worktop specialist measures. The exact process depends on the project and material.
Do not assume worktop installation can happen on the same day as cabinetry.
Templating and fabrication
The specialist measures the installed cabinets and prepares the worktop for manufacturing. Sink, hob, overhangs, joins and upstands must be confirmed at this stage.
At COSTAHAUS, a typical worktop installation is often around ten days after final measurement, but the actual schedule depends on the supplier and must be confirmed for the order.
Appliances and finishing
Appliances, tap connections, silicone finishing and final adjustments need to be coordinated with the fitter, worktop team and relevant qualified trades. Some appliances may be positioned earlier, but final connection depends on access and completion of adjacent work.
Leave time for commissioning, checking doors and drawers and recording any outstanding details.
How do I avoid delays?
Agree the responsibilities for plumbing, electrical changes, demolition, furniture delivery, fitting and worktop installation before works begin. Keep the approved kitchen plan and contact details available on site.
If you are abroad, appoint someone who can provide access and authorise necessary decisions within an agreed scope.